From: Griffith, Mike [mgriffith@majortool.com] Sent: Wednesday, April 12, 2006 10:32 AM To: Bob Simmons Cc: Phil Heitzenroeder; NKHFlowen@aol.com; Bowling, Kevin Subject: RE: Clarification on Which MCWFs will Have the Proposed Lifting Holes Bob, The lifting holes would be incorporated into C6 and all of the A and B shims. C5 is beyond this. Thanks. ________________________________ From: Bob Simmons [mailto:bsimmons@pppl.gov] Sent: Thursday, April 06, 2006 4:11 PM To: Griffith, Mike Cc: Phil Heitzenroeder; NKHFlowen@aol.com Subject: Clarification on Which MCWFs will Have the Proposed Lifting Holes Hi Mike, Phil may have already contacted you, but before we finalize the attached draft RFD-14-019, we need to make sure which MCWFs will have the lifting holes. We already know that C1 thru C4 did not, but am not sure whether C5 and later ones will have the holes. Until we get this clarification, we cannot proceed with this RFD. Please advise. Thanks, Bob S. Bob Simmons NCSX Systems Engineering Support Manager Princeton Plasma Physics Laboratory (PPPL) Tel #: (609) 243-2766 Fax #: (609) 243-3030