13 August 2003
Project cost will
likely under run this FY driven by the slippage of final design tasks as well
as late release of prototype fabrication (4 vendors).
Budget (incl carryover) Cost
thru July
PPPL
MIE 6,879 2,694
ACD 2,757 2,696
Total 9,635 5,390
ORNL
MIE 1,320 539
ACD 790 569
Total 2,110 1,109
Total Project
MIE 8,199 3,233
ACD 3,547 3,265
Total 11,745 6,499
Schedule slippages
evident in the key stellarator core design and R&D tasks now extend into
September which could impact the final documentation, reviews and PDR
preparation tasks. See the enclosed schedule analysis and schedule barcharts
for details.
Please let me know
of any corrections or misinterpretations.
Thanks,
Ron