13 August 2003

 

Analysis

 

Project cost will likely under run this FY driven by the slippage of final design tasks as well as late release of prototype fabrication (4 vendors).

 

              Budget (incl carryover)           Cost thru July

PPPL

MIE        6,879                                       2,694

ACD       2,757                                       2,696

Total       9,635                                       5,390

 

ORNL

MIE        1,320                                          539

ACD          790                                          569

Total       2,110                                       1,109

 

Total Project

MIE        8,199                                       3,233

ACD       3,547                                       3,265

Total    11,745                                       6,499

 

Schedule slippages evident in the key stellarator core design and R&D tasks now extend into September which could impact the final documentation, reviews and PDR preparation tasks. See the enclosed schedule analysis and schedule barcharts for details.

 

Please let me know of any corrections or misinterpretations.

 

Thanks,

Ron