Folks, Attached is the
current progress assessment of NCSX through MARCH.
SCHEDULE: We continue to be
about 2-3 months behind our original baseline
plan. Many tasks in support
of the VV/MCC PDR do not appear to support the
June 23rd date. A critical
path plot is included this month for project
engineering, WBS 12 and 14
managers to access the impact of these tasks.
(see summary analysis and
detailed barcharts for specific task progress).
COST PERFORMANCE: The
project's cost performance (CPI) has slipped from .96
in Jan, .91 in Feb to .84 in
Mar. This slip was generally seen across all
WBS elements. (The Cost
Performance Index (CPI) = .84, which translates into
accomplishing $84 worth of
work for every $100 spent).
BUDGET: Consistent with
being behind schedule the project continues to under
spend. Even with the 4 major
R&D contracts beginning to accrue cost, the
MIE/Research Prep project is
still facing a potential under run this fiscal
year of approx $1.3m ($785k PPPL and $540k ORNL). Many of these
projected
under runs are driven by the
institutional need to reduce discretionary
(M&S) spending. However,
efforts are underway to identify and accelerate
project scope that is labor
intensive. (see Budget status sheet)
Ron