ECP Number |
ECN? |
RFD? |
Title |
Date Approved or
Disapproved |
Impacted WBS Elements |
Type of Impact (Tech,
Cost, or Schedule) |
|
|
|
|
|
|
|
032 |
|
X |
RFD-14-006 - permit
2.5" and 3.5" pipe to be manufactured from ASTM 625 plate |
5/27/2005 |
12 |
Technical |
031 |
|
|
DOE Directed
Rebaseline |
|
All |
Cost & Schedule |
030 |
|
|
Planning Changes for
Risk Management |
5/4/2005 |
All |
Technical, Cost, &
Schedule |
029 |
|
|
Retirement of Risks for VVSA Forming Dies
and Twisted Racetrack Assembly |
4/21/2005 |
12 & 14 |
Cost |
028 |
|
X |
RFD-14-001 -
Relocation of Pattern/Casting ID Number |
3/30/2005 |
14 |
Technical |
027 |
X |
X |
RFD-12-002R1 -
Substitution of Sch10 Pipe for Sch40 Pipe for the 2.5" Pipe |
3/24/2005 |
12 |
Technical |
026 |
X |
|
MCWF Fast Response |
3/14/2005 |
141 |
Technical |
025 |
|
X |
RFD-12-001 -
Manufacture of the 6", 8" and 10" Pipe from ASTM 625 Plate |
3/10/2005 |
12 |
Technical |
024 |
|
|
Miscellaneous
Rescheduling and Contingency Draw for Added and Re-Estimated Scope |
3/7/2005 |
12, 13, 81 & 82 |
Technical, Cost, &
Schedule |
023 |
|
|
MCWF Minimum
Mechanical Properties |
2/17/2005 |
141 |
Technical |
022
R1 |
X
Y |
|
TRC Design Updates |
R1 - 2/3/2005 |
142 |
Technical, Cost, &
Schedule |
021 |
|
|
Job Close-Out &
Contingency Drawdown |
1/31/2005 |
12, 141, 142, & 84 |
Cost & Schedule |
020 |
X |
|
Resolution of
MCWF Questions (Dec-2004) |
1/14/2005 |
141 |
Technical |
019 |
X
Y |
|
VVSA Contract Addenda 3-1
though 3-3 |
1/25/2005 |
121 |
Technical |
018 |
|
|
FY005 Replanning Baseline |
11/19/2004 |
12, 14, 15, 18, 19,
3, 4, 5, & 7 |
Technical, Cost, &
Schedule |
017R1 |
X |
|
VVSA Inner Support Bosses |
11/9/2004 |
121 |
Technical |
016R1 |
|
|
Reprogramming for FY2004 Closeout |
11/9/2004 |
121, 133, 141, 142,
144, 19, 21, 432, 612, 614, & 82 |
Technical, Cost, &
Schedule |
015 |
X |
|
Final Technical Scope of MCWF |
9/17/2004 |
141 |
Technical |
014 |
|
|
CD-3 Replanning |
9/20/2004 |
12, 14, 187, 25, 3,
4, 5, 62, 64, 81, 82, 84, & 85 |
Technical, Cost, &
Schedule |
013 |
X |
|
Modifications to VV Joint R&D Seals and End Pieces |
7/30/2004 |
121 |
Technical &
Cost |
012 |
X |
|
MCWF Lead Block and Support Modifications |
7/30/2004 |
141 |
Technical |
011 |
|
|
Rebaseline for Modular Coil WAFs |
7/28//2004 |
14 |
Cost & Schedule |
010 |
X |
|
Prototype Winding Form Poloidal Break Geometry |
6/28//2004 |
141 |
Technical |
009 |
|
|
Reprogramming |
7/8/2004 |
141, 142, & 185 |
Technical, Cost, &
Schedule |
008 |
|
|
Update of the Technical Baseine to Reflect the
VVSA and MCWF FDR Design Configuration |
6/23/2004 |
121, 141, & 185 |
Technical, Cost, &
Schedule |
007 |
X |
|
Twisted Racetrack VPI Groove Depth |
4/28/2004 |
141 |
Technical |
006 |
|
|
Updated Cost and Schedule Estimate for Design and
R&D |
4/29/2004 |
121, 13, 141, 144, &
144 |
Technical, Cost, &
Schedule |
005 |
|
|
Revised Estimates fro Design, R&D, and Tooling |
3/15/2004 |
12, 14, 18, 2, 3, 4,
5, 6, 7, & 8 |
Technical, Cost, &
Schedule |
004 |
|
|
CD-2 Cost and Schedule Baseline |
2/28//2004 |
12, 14, 16, 18, 2, 3,
4, 5, 6, 7, & 8 |
Technical, Cost, &
Schedule |
003 |
|
|
FY2004 Management Reserve Distributions |
1/20/2004 |
Various WBS Elements |
Cost |
002 |
|
|
Change in MCWF Design |
11/18/2003 |
141 |
Technical |
001 |
|
|
Revision 1 to the General Requirements Document |
1/23/2004 |
1, 2, 3, 4, 5, 6, & 7 |
Technical |
|
|