WBS 2 Auxiliary Systems

CD-2 Baseline

WBS Level 3 WBS Level 4
WBS 2 -Auxiliary Systems  

WBS 21 - Fueling Systems

  • Summary Information - Not Changed Since PDR Baseline

  • Contingency - Not Changed Since PDR Baseline

  • Backup - Not Changed Since PDR Baseline

    • Only escalation due to re-sequencing of activities to conform to funding constraints => no change in estimate

     

 
WBS 22 - Vacuum Pumping Systems
  • Summary Information - Not Changed Since PDR Baseline

  • Contingency - Not Changed Since PDR Baseline

  • Backup - Not Changed Since PDR Baseline

    • Only escalation due to re-sequencing of activities to conform to funding constraints => no change in estimate
 
 
WBS 23 - Wall Conditioning Systems - NOT in BASELINE  
WBS 24 - RF Heating Systems  - NOT in BASELINE  
WBS 25 - Neutral Beam Systems
  • Summary Information - Not Changed Since PDR Baseline

  • Contingency - Not Changed Since PDR Baseline

  • Backup - Not Changed Since PDR Baseline

    • Only escalation due to re-sequencing of activities to conform to funding constraints => no change in estimate
 
WBS 26 - ECH Systems - NOT in BASELINE