WBS 3 Diagnsotic Systems

CD-2 Baseline

WBS Level 3 WBS Level 4
WBS 3 -Diagnostic Systems  

WBS 31 - Magnetic Diagnostic Systems

  • Summary Information - Not Changed Since PDR Baseline

  • Contingency - Not Changed Since PDR Baseline

  • Backup - Not Changed Since PDR Baseline

    • Only escalation due to re-sequencing of activities to conform to funding constraints => no change in estimate
 
WBS 32 - Fast Particle Diagnostic Systems - NOT in BASELINE  
WBS 33 - Impurity Diagnostic Systems - NOT in BASELINE  
WBS 34 - MHD Diagnostic Systems  - NOT in BASELINE  
WBS 35 - Profile Diagnostic Systems  - NOT in BASELINE  
WBS 36 - Edge & Divertor Diagnostic Systems
  • Summary Information - Not Changed Since PDR Baseline

  • Contingency - Not Changed Since PDR Baseline

  • Backup - Not Changed Since PDR Baseline

    • Only escalation due to re-sequencing of activities to conform to funding constraints => no change in estimate
 
WBS 37 - Turbulence Diagnostic Systems - NOT in BASELINE  
WBS 38 - Electron Beam (EB) Mapping Systems
  • Summary Information - Not Changed Since PDR Baseline

  • Contingency - Not Changed Since PDR Baseline

  • Backup - Not Changed Since PDR Baseline

    • Only escalation due to re-sequencing of activities to conform to funding constraints => no change in estimate
 
WBS 39 - Diagnostic Systems Integration
  • Summary Information - Not Changed Since PDR Baseline

  • Contingency - Not Changed Since PDR Baseline

  • Backup - Not Changed Since PDR Baseline

    • Schedule stretch-out (total of 8 months) due to accommodation of PDR recommendations, PBR recommendations, and CD-4 scope inclusions