WBS 6 Facility Systems

CD-2 Baseline

WBS Level 3 WBS Level 4
WBS 6 -Facility Systems

WBS 61 - Water Cooling  Systems

WBS 611 - C-Site Water Cooling Systems
  • Summary Information - Not Changed Since PDR Baseline

  • Backup - Not Changed Since PDR Baseline

    • Only escalation due to re-sequencing of activities to conform to funding constraints => no change in estimate

WBS 612 - Neutral Beam Water Cooling Systems

  • Summary Information - Not Changed Since PDR Baseline

  • Backup - Not Changed Since PDR Baseline

    • Only escalation due to re-sequencing of activities to conform to funding constraints => no change in estimate

WBS 613 - Vacuum Pumping Water Cooling Systems

  • Summary Information - Not Changed Since PDR Baseline

  • Backup - Not Changed Since PDR Baseline

    • Only escalation due to re-sequencing of activities to conform to funding constraints => no change in estimate

WBS 614 - Bakeout Water Systems

  • Summary Information - Not Changed Since PDR Baseline

  • Backup - Not Changed Since PDR Baseline

    • Only escalation due to re-sequencing of activities to conform to funding constraints => no change in estimate

WBS 615 - Diagnostic Water Cooling Systems

  • Summary Information - Not Changed Since PDR Baseline

  • Backup - Not Changed Since PDR Baseline

    • Only escalation due to re-sequencing of activities to conform to funding constraints => no change in estimate
WBS 62 - Cryogenic Systems
  • Summary Information - Not Changed Since PDR Baseline

  • Contingency - Not Changed Since PDR Baseline

  • Backup - Changes since PDR

    • PDR recommendations to correct estimate error and reassess vaporizers

    • Only escalation due to re-sequencing of activities to conform to funding constraints => no change in estimate
 
WBS 63 - Utility Systems
  • Summary Information - Not Changed Since PDR Baseline
  • Contingency - Not Changed Since PDR Baseline
  • Backup - Not Changed Since PDR Baseline
    • Only escalation due to re-sequencing of activities to conform to funding constraints => no change in estimate
 
WBS 64 - Bakeout Systems
  • Summary Information - Not Changed Since PDR Baseline
  • Contingency - Not Changed Since PDR Baseline
  • Backup - Not Changed Since PDR Baseline
    • Only escalation due to re-sequencing of activities to conform to funding constraints => no change in estimate
 
WBS 65 - Facility Systems Integration  
WBS 66 - Room Temperature Coil Cooling Systems - NOT in BASELINE