WBS 7 Test Cell Preparation and Machine Assembly

CD-2 Baseline

WBS Level 3 WBS Level 4
WBS 7 -Test Cell Preparation and Machine Assembly
  • Summary Information - Not Changed Since PDR Baseline 
  • Backup - Changes since PDR
    • WBS 73, WBS 74, & WBS 75 - Escalation due to re-sequencing of activities to conform to funding constraints => no change in estimate
    • WBS 742 - Schedule stretch-out (total of 8 months) due to accommodation of PDR recommendations, PBR recommendations, and CD-4 scope inclusions
    • PBR recommendation to provide additional time for final alignment of field periods
    • CD-4 scope inclusions to include:
      • Power testing and e-beam mapping;
      • Cryostat installation, testing, and cooldown; and
      • Cold power testing
 

WBS 71 - Shield Wall Reconfiguration

 

WBS 72 - Control Room Refurbishment

 

WBS 73 - Platform Design & Fabrication

 

WBS 74 - Construction Management

WBS 741 - Planning Prior to Machine Assembly
  • Summary - Only in FY2004 WAFs

WBS 742 - Construction Management

  • Summary

WBS 75 - Test Cell and Basement Assembly Operations

 

WBS 76 - Tooling Design & Fabrication

 

WBS 77 - Measurement Systems - NOT in BASELINE