WBS 11:  Paul Goranson WBS 16:  Dave Williamson Date of Agreement:   December 17, 2002
Project Engineer (s):  Brad Nelson (WBS 1) Systems Engineer:  Bob Simmons

Type of Interface

Scope

Lead Responsibility

Deliverable

Due Date

WAF Task Reference

Design Studies None

 

     
Functional Interfaces None

 

     
Physical Interfaces (1) Attachment schemes and envelopes between trim coil upgrade and electrical leads (WBS 162) and coil protection system interfaces (WBS 163) not included in WBS 4.

WBS 11 (Goranson)

Separate ICD. Needs to be done in time to incorporate into VV design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR.