WBS 11:  Paul Goranson WBS 3:  Dave Johnson Date of Agreement:   December 17, 2002
Project Engineer (s):  Brad Nelson (WBS 1) & Larry Dudek (Ancillary Systems) Systems Engineer:  Bob Simmons

Type of Interface

Scope

Lead Responsibility

Deliverable

Due Date

WAF Task Reference

Design Studies None

 

     
Functional Interfaces None

 

     
Physical Interfaces (1) Attachment schemes for in-vessel diagnostics attached/embedded in PFCs.

WBS 11 (Goranson)

Separate ICD. Needs to be done in time to incorporate into  VV design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR.