WBS 11: Paul Goranson | WBS 4: Raki Ramakrishnan | Date of Agreement: December 18, 2002 |
Project Engineer (s): Brad Nelson (WBS 1) & Larry Dudek (Ancillary Systems) | Systems Engineer: Bob Simmons |
Type of Interface |
Scope |
Lead Responsibility |
Deliverable |
Due Date |
WAF Task Reference |
Design Studies | None |
|
|||
Functional Interfaces | None |
|
|||
Physical Interfaces | (1) Attachment schemes and envelopes between trim coil upgrade and electrical leads (WBS 162) and coil protection system interfaces (WBS 163 & WBS 4). |
WBS 11 (Goranson) |
Separate ICD. | Needs to be done in time to incorporate into VV design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR. |