WBS 12:  Paul Goranson WBS 18:  Jim Chrzanowski Date of Agreement:   December 17, 2002
Project Engineer (s):  Brad Nelson (WBS 1) Systems Engineer:  Bob Simmons

Type of Interface

Scope

Lead Responsibility

Deliverable

Due Date

WAF Task Reference

Design Studies (1) VV field joint study.

WBS 12 (Goranson)

[Mike Viola]

Memo - Project will use the results as basis for joint design. Needs to be done in time to incorporate into VV design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR.  
Functional Interfaces None.        
Physical Interfaces (1) Assembly related attachments, special tooling needs, lifting points, clearance requirements for field period assembly.

WBS 18 (Chrzanowski)

Separate ICD. Needs to be done in time to incorporate into VV design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR.  
  (2) Assembly related attachments, special tooling needs, lifting points, clearance requirements, and measurement points for final assembly.

WBS 18 (Chrzanowski)

Separate ICD. Needs to be done in time to incorporate into VV design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR.  
  (3) Clearance requirements, special tooling, measurement provisions for adding cooling/heating lines and insulation prior to assembly.

WBS 18 (Chrzanowski)

Separate ICD. Needs to be done in time to incorporate into VV design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR.  
  (4) Assembly related attachments special tooling requirements, clearance requirements, measurement provisions for adding VV port extensions.

WBS 18 (Chrzanowski)

Separate ICD. Needs to be done in time to incorporate into VV design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR.