| WBS 12: Paul Goranson | WBS 4: Raki Ramklrishnan | Date of Agreement: December 17, 2002 |
| Project Engineer (s): Brad Nelson (WBS 1) & Larry Dudek (Ancillary Systems) | Systems Engineer: Bob Simmons |
|
Type of Interface |
Scope |
Lead Responsibility |
Deliverable |
Due Date |
WAF Task Reference |
| Design Studies | None. | ||||
| Functional Interfaces | None. | ||||
| Physical Interfaces | (1) VV grounding connection to NCSX grounding system outside the cryostat. |
WBS 12 (Goranson) |
Separate ICD. | Needs to be done in time to incorporate into VV design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR. |