WBS 12: Paul Goranson | WBS 6: Larry Dudek (61) & Mike Kalish (64) | Date of Agreement: December 17, 2002 |
Project Engineer (s): Brad Nelson (WBS 1) & Larry Dudek (Ancillary Systems) | Systems Engineer: Bob Simmons |
Type of Interface |
Scope |
Lead Responsibility |
Deliverable |
Due Date |
WAF Task Reference |
Design Studies | (1) Study to determine whether He or H20 cooling of vacuum vessel. |
WBS 12 (Goranson) |
Memo - Project will use as basis for establishing vacuum vessel cooling scheme and interface requirements. | Needs to be done well in advance of when WBS 12 performance specification is due. | |
Functional Interfaces | (1) VV cooling requirements. |
WBS 12 (Goranson) |
Maximum cooling requirements incorporated in WBS 12 performance specification. | Needs to be done in advance of [1] when thermal analysis and cooling system is planned and [2] when WBS 12 performance (design-to) spec is due. | |
Physical Interfaces | (1) Attachment scheme to WBS 6 connections outside the cryostat. |
WBS 12 (Goranson) |
Separate ICD. | Needs to be done in time to incorporate into VV design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR. |