WBS 12:  Paul Goranson WBS 6:  Larry Dudek (61) & Mike Kalish (64)  Date of Agreement:   December 17, 2002
Project Engineer (s):  Brad Nelson (WBS 1) & Larry Dudek (Ancillary Systems) Systems Engineer:  Bob Simmons

Type of Interface

Scope

Lead Responsibility

Deliverable

Due Date

WAF Task Reference

Design Studies (1) Study to determine whether He or H20 cooling of vacuum vessel.

 WBS 12 (Goranson)

Memo - Project will use as basis for establishing vacuum vessel cooling scheme and interface requirements. Needs to be done well in advance of when WBS 12 performance specification is due.  
Functional Interfaces (1) VV cooling requirements.

 WBS 12 (Goranson)

Maximum cooling requirements incorporated in WBS 12 performance specification. Needs to be done in advance of [1] when thermal analysis and cooling system is planned and [2] when WBS 12 performance (design-to) spec is due.  
Physical Interfaces (1) Attachment scheme to WBS 6 connections outside the cryostat.

WBS 12 (Goranson)

Separate ICD. Needs to be done in time to incorporate into VV design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR.