WBS 133: Mike Kalish | WBS 84: Mike Zarnstorff | Date of Agreement: December 17, 2002 |
Project Engineer (s): Brad Nelson (WBS 1) & Hutch Neilson (Project Mgmt) | Systems Engineer: Bob Simmons |
Type of Interface |
Scope |
Lead Responsibility |
Deliverable |
Due Date |
WAF Task Reference |
Design Studies | None |
|
|||
Functional Interfaces |
(1) Performance requirements for internal trim coils upgrades. |
WBS 11 (Goranson)
|
Maximum performance requirememts for internal trim coils incorporated into WBS 11 and WBS 12 performance specications. | Needs to be done in advance of when the WBS 12 performance (design to) specification is due and in time to incorporate into the VV design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR. | |
Physical Interfaces | None |