WBS 14:  Dave Williamson WBS 16:  Geoff Gettelfinger  Date of Agreement:   December 17, 2002
Project Engineer (s):  Brad Nelson (WBS 1)  Systems Engineer:  Bob Simmons

Type of Interface

Scope

Lead Responsibility

Deliverable

Due Date

WAF Task Reference

Design Studies None

 

     
Functional Interfaces (1) Modular coil fault design conditions.

 WBS 14 (Williamson)

Maximum fault conditions incorporated into the WBS 14 & WBS 16 performance specifications. Needs to be done in advance of [1] when the structural analysis is planned and [2] when WBs 14 & WBS 16 performance (design to) specs are due.  
Physical Interfaces (1) LN2 cooling connections to LN2 manifold inside cryostat (WBS 161).

 WBS 14 (Williamson)

Separate ICD. Needs to be done in time to incorporate into modular coil design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR.  
  (2) Electrical leads connections for electrical leads within the cryostat (WBS 162).

 WBS 14 (Williamson)

Separate ICD. Needs to be done in time to incorporate into modular coil design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR.  
  (3) Attachment schemes and envelopes between modular coils and coil protection system interfaces (WBS 163) not included in WBS 4.

 WBS 14 (Williamson)

Separate ICD. Needs to be done in time to incorporate into modular coil design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR.