WBS 14:  Dave Williamson WBS 17:  Geoff Gettelfinger  Date of Agreement:   December 17, 2002
Project Engineer (s):  Brad Nelson (WBS 1)  Systems Engineer:  Bob Simmons

Type of Interface

Scope

Lead Responsibility

Deliverable

Due Date

WAF Task Reference

Design Studies None

 

     
Functional Interfaces (1) Heat loads from modular coils to cryostat boundary (WBS 171).

 WBS 14 (Williamson)

Maximum fault conditions incorporated into the WBS 14 & WBS 17 performance specifications. Needs to be done in advance of [1] when the structural analysis is planned and [2] when WBs 14 & WBS 17 performance (design to) specs are due.  
Physical Interfaces (1) Radial build for filler insulation around ports and between coils.

 WBS 17 (Gettelfinger)

Separate ICD. Needs to be done in time to incorporate into modular coil design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR.