WBS 14:  Dave Williamson WBS 5:  Gary Oliaro  Date of Agreement:   December 17, 2002
Project Engineer (s):  Brad Nelson (WBS 1) & Larry Dudek (Ancillary Systems) Systems Engineer:  Bob Simmons

Type of Interface

Scope

Lead Responsibility

Deliverable

Due Date

WAF Task Reference

Design Studies None

 

     
Functional Interfaces None

 

     
Physical Interfaces (1) Modular coil local I&C connections to central I&C systems.

 WBS 14

(Williamson)

Separate ICD. Needs to be done in time to incorporate into vacuum vessel design and associated drawings, which have to be reviewed and promoted to Preliminary Design Release Level prior to the PDR.