Name of Plan

Currently Approved Revision

  Drafts/Revisions in Process

Peer Reviews of Initial Issue

Plans Approved by DOE

     
 Acquisition Execution Plan (AEP) Revision 0    
Project Execution Plan (PEP)

Revision 3

Approval Letter (Aug 11, 2005)

 

 

Plans Approved by Project

     
Systems Engineering Management Plan (SEMP)

Revision 0

 

5/15/2003
Quality Assurance Plan (QAP)

Revision 1

 

11/1/2002
Configuration Management Plan (CMP) Revision 2   12/17/2002
Data Management Plan (DMP) Revision 2   3/31/2003
Document and Records Plan (DOC)

Revision 3

  3/14/2003
Interface Control Management Plan (ICMP)

Revision 1

 

12/19/2002
Reliability, Availability, and Maintainability Plan (RAM)

Revision 0

 

 
Risk Management Plan (RMP)

Revision 0

 

 
Safe Startup and Control Plan (SSU) Revision 0 In Signature Cycle  
Experimental Plan (EP)

 

 Version 3 - Being Reviewed and Updated

 
Radiation Safety Plan (RSP)

 

NOT YET DRAFTED

 
Training Plan (TRNG)

Revision 2

 

 