When we promote
drawings to fabrication within Intralink we pull in
all parts and assemblies needed to make the drawings and they (along with the
drawings) are promoted to a particular release level (fabrication as the final
step, other than AS Built). The
revision number must be assigned if they are a value other than 0; the version
numbers are automatically assigned.
This will also include data curves if they are needed or skeleton parts
(used in making the port cuts). We
do not store the STEP or IGES files in the promotion process since they can be
directly made from the properly stored ProE
files. When Jerry stamps and signs
the drawings he (effectively) is stating that the data that supports the
drawings are included in the promoted drawing package. I’ve set up a process where he must look
at the listing presented in Intralink to verify that
all items are present.
Realistically I’m not sure that he can tell but must assume that they are
there…. Not sure how to improve on it.
-Tom
-----Original
Message-----
From: Wayne T.
Reiersen
Sent: Wednesday, May
26, 2004 9:57 AM
To: Thomas G.
Brown; Bob Simmons
Subject: RE:
Need Drawing and Rev # for Weld Joint R&D Task
How are we
effecting change control on design data such as Pro/E models that are not
covered by our drawing control procedures (e.g. PDF and have Jerry
sign)?
-----Original
Message-----
From: Thomas G.
Brown
Sent: Wednesday, May 26,
2004 10:44 AM
To: Bob Simmons;
Michael E. Viola; Wayne T. Reiersen; 'goransonpl@y12.doe.gov'
Cc: Frank A. Malinowski; 'Nelson_Brad';
Arlene E. White; Phil Heitzenroeder; 'Larry L. Sutton'
Subject: RE: Need Drawing and Rev # for
Weld Joint R&D Task
I just
wanted to interject in the conversation one additional piece of
information. We now not only supply drawings to the vendors but also a lot
of other data. In addition to drawings we include all Pro/E parts and
assemblies as well as STEP files and when appropriate point text files and
surface IGES files. So the information provided is extensive. This
should be listed in a spread sheet format (as David did for the MC’s for the
FDR). It seems appropriate that the spread sheet listing would be an
addendum to the Spec.
-Tom
-----Original
Message-----
From: Bob Simmons
Sent: Wednesday, May 26, 2004
9:27 AM
To: Michael E. Viola;
Wayne T. Reiersen; Thomas G. Brown; 'goransonpl@y12.doe.gov'
Cc: Frank A. Malinowski; 'Nelson_Brad';
Arlene E. White; Phil Heitzenroeder; 'Larry L. Sutton'
Subject: RE: Need Drawing and Rev # for
Weld Joint R&D Task
Mike, et
al:
Wayne and
I think we have a reasonable solution here:
(1) If SOW and Spec, then
contract needs to reference both documents and their applicable revision
number. Spec needs to list all the drawings and their rev numbers since it is the technical basis of the
design. Since the spec exists, the SOW need not reference any
drawings at all – it needs to merely point to the “latest version of the
spec”. If conflicts arise, the contract shall take precedent. If we
add a drawing, change a drawing, both the spec and drawings (impacted ones only)
need to be revised. We will not accept revising drawings without also
revising spec.
(2) If no spec, then the
SOW need not reference the specific drawings and rev number, but the contract
MUST. If not, then the SOW must be the ultimate source
document.
So in case
of the weld R&D task, the SOW may have to be modified to provide correct
list of drawings but will need to point to the contract as the ultimate source
document. It needs to also clearly state that in the event there is a
discrepancy between the SOW and the contract, the contact shall take
precedent. I will need to modify the SOW to update the drawing list (but
with no rev #) and to add the appropriate contract precedence
wording.
Bob
S.
Bob
Simmons
NCSX
Systems Engineering Support Manager
Princeton
Plasma Physics Laboratory (PPPL)
Tel #:
(609) 243-2766
Fax #:
(609) 243-3030
-----Original
Message-----
From: Michael E.
Viola
Sent: Wednesday, May 26,
2004 10:16 AM
To: Wayne T.
Reiersen; Bob Simmons; Thomas G. Brown; 'goransonpl@y12.doe.gov'
Cc: Frank A. Malinowski; 'Nelson_Brad';
Arlene E. White; Phil Heitzenroeder; 'Larry L. Sutton'
Subject: RE: Need Drawing and Rev # for
Weld Joint R&D Task
Wayne,
A few days
ago Larry Sutton and Phil were chatting and realized that it would be a
lot easier if the SOW referred to the Contract for the list of drawings.
That way when the drawings were updated it involved Larry simply sending out one
amendment instead of revising the SOW or SPEC with a half dozen
signatures. Wouldn't that be OK?
Mike
From: Wayne T.
Reiersen
Sent: Wednesday, May
26, 2004 10:03 AM
To: Bob
Simmons; Michael E. Viola; Thomas G. Brown; 'goransonpl@y12.doe.gov'
Cc: Frank A. Malinowski; 'Nelson_Brad';
Arlene E. White
Subject: RE:
Need Drawing and Rev # for Weld Joint R&D Task
Let’s be
clear here. The SOW should never take the place of a spec. The SOW
defines the work to be performed. The spec defines the technical product
along with the drawings identified in the spec. If the product is
completely defined by the drawings, then a spec is not required. If there
is a spec, then the SOW needs to point to it. If there is no spec but only
drawings, then the SOW needs to point directly to the drawings.
-----Original
Message-----
From: Bob Simmons
Sent: Wednesday, May 26, 2004
8:24 AM
To: Michael E. Viola;
Thomas G. Brown; goransonpl@y12.doe.gov
Cc: Wayne T. Reiersen; Frank A. Malinowski;
Nelson_Brad; Arlene E. White
Subject: Need Drawing and Rev # for Weld
Joint R&D Task
Mike, Tom, and
Paul:
Since the SOW will take the place of
a spec and will be a contract document, I think that we will need to include the
correct drawing numbers and revision numbers in the SOW. When drawings
ready for signature (or signed), please send me the final list with rev # and I
will revise the SOW and quickly send it around for electronic
signature.
Thanks,
Bob S.
Bob
Simmons
NCSX Systems Engineering Support
Manager
Princeton Plasma Physics Laboratory
(PPPL)
Tel #: (609)
243-2766
Fax #: (609)
243-3030