From: Henry W. Kugel [hkugel@pppl.gov]
Sent: Tuesday,
September 17, 2002 12:00 PM
To: reiersen@pppl.gov
Cc: Ron
Strykowsky; Mike Zarnstorff; John Schmidt; Jim Lyon; wblanchard@pppl.gov;
tstevenson@pppl.gov
Subject: re Review of GRD
Wayne,
The WBS 2 Subsystem coordinators have forwarded to you the below summaries
of our WBS2 discussions of the GRD draft.
In addition, I wish note the following:
1) Table 3-2 refers to vacuum diagnostics checkout, but these vacuum
diagnostics do not seem to be listed.Therefore, under
3.2.1.1.2 Vacuum Requirements
3.2.1.1.2.1 Base Pressure
Insert after the below W.Blanchard sentence, the following
sentence:
(Blanchard)......., the device should produce a base pressure in the low
10-8 Torr of impurity gases at 293K. The partial pressure
components of the base pressure shall be measured with a Residual Gas
Analyzer(RGA) mounted at a location on one of the Pumpducts near the
Turbomolecular pumps. Each Sector shall have a standard, magnetically shielded,
nude Ion Gauge mounted as close to the first wall midplane as possible, and a
nearby port shall be provided for at least one Fast Neutral Pressure gauge.
These gauges shall be calibrated using 3 Capacitance Manometers (1, 10, and 1000
Torr ranges) mounted near the RGA. All
diagnostics...(Blanchard).
2) I have noted before in response to port requests that each Sector
requires at least
one port for a standard Ion Gauge,
one port for a Fast Neutral pressure gauge,
one port for a GDC anode,
one port for GDC Preionization Filaments
one port for a Gas Injector
3) RE: the M.Zarnstorff/H.Kugel Neutral Beam Telcom of 07-AUG-02. Typically
it is necessary to close the NBI TIV's during Between-Shot-GDC. This could be
avoided by a installing inboard of the TIV, a high conductance shutter, to limit
GDC gas flow into the NB Beamline. This appears to be doable but requires
analysis of interlock requirements, as-built conductance, engineering costs
etc., and hence, is not recommended to be a baseline requirement, although
we intend to vigorously investigate this option.
-Henry
At 2:27 PM -0400 9/16/02, Wayne Reiersen wrote:
Cc: "Ron Strykowsky"
<rstrykowsky@pppl.gov>,
"Mike Zarnstorff" <mzarnstorff@pppl.gov>,
"John
Schmidt" <jschmidt@pppl.gov>, "Jim Lyon"
<lyonjf@ornl.gov>
Subject: Review of GRD and SEMP
Date: Mon, 16
Sep 2002 14:27:42 -0400
X-Priority: 3 (Normal)
Importance:
Normal
Folks,
Review comments on the GRD were due on 9/6.
Review comments on the SEMP
were due 9/13. If you have not already
critically reviewed those documents
and provided comments, please do so at
your earliest convenience. This is
especially true for the GRD - we
need to make a punch list of issues and get
people mobilized to address
them before we come to closure on that document.
Thanks for you
attention to this matter,
Wayne
At 1:39 PM -0400 9/9/02, William Blanchard
wrote:
X-Sender: wblancha@pobox.pppl.gov
Date: Mon,
09 Sep 2002 13:39:11 -0400
To: wreiersen@pppl.gov
From: William
Blanchard <wblanchard@pppl.gov>
Subject: GRD Comments
Cc:
hkugel@pppl.gov, mzarnstorff@pppl.gov
Wayne, A few comments
on the GRD. -Bill
3.2.1.1.2.1 Base Pressure: The initial surface
area of the vacuum vessel for first plasma will be approximately 40 M^2 and
will be increased significantly in its final configuration. All materials in
vacuum should be high vacuum compatible. With a target leak rate in the range
of (1-2)x10-5 T-l/sec or less and a pumping speed of 2600 l/sec or better and
a well baked and conditioned machine, the device should produce a base
pressure in the low 10-8 Torr of impurity gases at 293K. All diagnostics that
are not to be left open permanently to the vacuum vessel should have their own
pumping system and all appendages, ports and diagnostics should have bakeout
capabilities to maintain very high vacuum conditions. All systems and
components either in vacuum or with a vacuum interface should be designed to
preclude trapped volumes and virtual leaks.
3.2.1.1.2.2 Pumping Speed:
delete "which is equal to or greater than that achieved on PBX-M."
3.2.1.2.1.1 Bakeout Background: Suggest that
it be pointed out that all systems and materials be compatible for the bakeout
temperature they will see for strength, compliance for expansion and vacuum
compatibility (developing leaks etc.).
3.2.1.2.1.2 Glow Discharge
Cleaning (GDC) (delete During Bakeout)
a) The facility shall
provide a glow discharge cleaning (GDC) capability with DC glow for indefinite
periods of time with the vacuum vessel and all components internal to the
vacuum vessel at room temperature and at their nominal bakeout temperatures.
All windows should have shutters to prevent coating during GDC. All large
ceramic breaks should be shielded to prevent coating and high resistance
shorts between different grounds.
3.2.1.4.4 PFC Configuration d) delete
"sealed"
3.2.1.4.7.2 Gas Injection
The gas injection system shall be
capable of injecting any one of three gases (or combination of gases) with a
maximum flow rate of at least 50 T-l/sec per injector. The device and facility
shall have a programmable gas injection system with feedback on real-time
density measurement.
3.3.1.2 Vacuum Compatibility
a) In-vessel
metallic components shall be electropolished when feasible
b) All in-vessel
components shall be degreased and cleaned as a minimum and baked when
practicable prior to installation.
c) All in-vessel materials shall be
approved by the Project for vacuum compatibility [3].
3.3.6
Environmental, Safety, and Health (ES&H) Requirements
Somewhere in this
section it should state that all vacuum windows of 4" or greater shall have
covers over them or otherwise be protected from accidental
implosions.
A few questions/comments:
* What are the standoff
voltages that systems are to be designed to?
* What is the grounding
scheme? What loop resistances can be tolerated? How are they going to be
monitored? Some systems should be designed with ease of removing grounds for
troubleshooting loop faults (diagnostics, thermocouples etc).
* It might be helpful for new drafts to have the
changes that were made in a different color to expedite
Date: Fri, 6 Sep 2002 14:35:45 -0400
To:
"Wayne Reiersen" <reiersen@pppl.gov>
From: Tim Stevenson
<tstevens@pppl.gov>
Subject: Re: Review of GRD
Cc:
hkugel@pppl.gov, hneilson@pppl.gov
Wayne,
In the GRD NBI section quoted below, the pulse
length of 1.2 seconds is mentioned as an upgrade. First, the existing NBI
system will pulse to 0.5 seconds, with more reliable results at 0.3 seconds.
No mention of this pulse length is included, but it is a very fixed limit of
this system.
Second, the upgrade to 1.2 seconds is a very big
leap in time, technology, and cost that includes upgrades to other auxiliary
subsystems also, like the water system. The facility should not be initially
designed to accommodate the 1.2 second system as stated because the costs will
be prohibitive for the initial beam phase and the upgrade to 4 beam phase.
Rather, the existing system should be installed so as not to prevent a future
upgrade to 1.2 seconds. This 1.2 second upgrade will require extensive
changes.
Henry and I had this conversation earlier today
so I write with his concurrence.
Regards,
Tim
3.2.1.4.6.1
Neutral Beam Heating
3.2.1.4.6.1.1 Initial NB Heating
Complement
Two of the four beamlines previously used on the PBX-M
project will be installed as part of the NCSX Fabrication Project. One will
be configured in the co-direction (the nominal direction of the plasma
current) and one in the counter-direction. The tangency radius shall be
inside the magnetic axis for the nominal 1.7T high beta equilibrium and
located such that the beam does not intercept the inboard first
wall.
3.2.1.4.6.1.2 Ultimate NB Heating Complement
a) The
facility shall be designed to accommodate neutral beam heating using the
four (4) beamlines previously used on PBX-M (as a future upgrade) in two
possible configurations: [1] 2 co- and 2 counter-directed beamlines and [2]
3 co- and 1 counter-directed beamlines.
b) The facility shall be designed
to accommodate an extended heating pulse duration of
1.2s.
--
H.W.Kugel, MS41,
B-304
e-Mail: hkugel@pppl.gov
Princeton Plasma Physics
Laboratory
Tel: (609) 243-3146
P.O. Box 451, Princeton, NJ
08543-0451
FAX: (609) 243-3248