Review
Title |
VVSA Product Spec Review |
Date |
08 April 2004 |
Cognizant
Engineer |
Paul Goranson for (Spec and
PVVS Plan), Mike Viola for (SOW) |
Responsible
Line Manager |
Wayne Reiersen |
Review Board Chairperson |
John Schmidt |
Review Board Members |
Phil Heitzenroeder, Frank Malinowski,
Mike Cole, Larry Dudek |
Invited Attendees |
Malinowski, Reiersen |
Other Attendees |
|
Charge |
-
Is the VVSA SOW suitable
for the production contract? Of particular importance is the degree of
PPPL control over the supplier's process: is the entire MIT/QA plan
PPPL - approved or just specified hold points and inspections? Also,
the extent and frequency of formal reporting required.
-
Is the product spec consistent with the design-to
requirements?
-
Does the product spec provide an adequate technical
basis for manufacture?
|
Design Review Material |
Announcement
VVSA Product Spec (as
amended during the review)
Chits and Disposition |
Review Board Report |
|
Items Reviewed |
|
Sat |
Unsat |
Comments |
Appropriate requirements identified
|
|
|
With resolution of chits |
Development plans and schedules |
|
|
Not addressed |
Regulatory compliance including USQD and NEPA |
|
|
Not addressed |
Disposition of CHITS from previous reviews |
|
|
Not applicable |
Cost
objectives |
|
|
Not addressed |
Other
review objectives addressed
(Attachment 4 of ENG-033) |
|
|
Not applicable |
Summary of Results
|
Review successful with resolution of CHITS
|
Disposition
(check
one) |
1 Acceptable |
Acceptable pending resolution of concerns -
CHITS identified above must be resolved prior to installation. |
1
Incomplete -
Additional design
work is required prior to another design review.
|
Cog Engineer Close-out
(check
when done) |
|
1
Action required by Disposition is complete |