Review
Title |
Final Assembly Plan Peer
Review |
Date |
15 April 2004 |
Cognizant Engineer |
Mike Cole |
Responsible Line Manager |
Brad Nelson |
Review Board Chairperson |
Erik Perry |
Review Board Members |
Wayne Reiersen, Tom Brown,
Steve Raftopoulos, Geoff Gettelfinger |
Invited Attendees |
Hutch Neilson, Larry Dudek,
Jim Chrzanowski, Dave Williamson, Paul Goranson |
Other Attendees |
Bob Simmons, Judy Malsbury, Phil
Heitzenroeder, Art Brooks, Paul Miller |
Charge |
Access the NCSX
stellarator core final assembly plan with respect to the following:
1. Do the motions of the
field period assemblies and vacuum vessel spool pieces required for
final assembly of the stellarator core maintain adequate clearances
among and between all the components?
2. Are the assembly
tooling requirements reasonable and achievable?
3. Are appropriate
provisions made for metrology and in-process sensors (i.e. motion
proximity, etc)?
4. Are the assembly
requirements defined for the base support structure? (plan includes PF
pre-placement, motions, accuracy, VV port extension provision, etc.)
5. Is the plan
documented in the final assembly procedure? |
Design Review Material |
Announcement
Presentation
Chits and Project
Disposition |
Review Board Report |
|
Items Reviewed |
|
Sat |
Unsat |
Comments |
Appropriate requirements identified
|
|
|
see chits 1-4
|
Development plans and schedules |
|
|
see chits 5 and 13 |
Regulatory compliance including USQD and NEPA |
|
|
|
Disposition of CHITS from previous reviews |
|
|
|
Cost
objectives |
|
|
|
Other
review objectives addressed
(Attachment 4 of ENG-033) |
|
|
Charge for review not fully
addressed |
Summary of Results
|
A potential assembly sequence
was presented as well as an analysis of minimum clearances between the
vacuum vessel spool piece and clamps. Fourteen chits were generated,
the most significant ones being the need to develop a leak checking
technique for the vacuum vessel field welds and the need to demonstrate
clearance among and between all of the components during assembly.
*Once all of these chits have
been closed-out, another peer review should be held with a review board that
includes several persons who have managed the construction of large devices.
|
Disposition
(check one) |
Acceptable |
Acceptable pending resolution of concerns -
CHITS identified above must be resolved prior to installation. |
Incomplete -
Additional work is required prior to another design review.
|
Cog Engineer Close-out
(check
when done) |
|
Action required by Disposition is complete |