        | Review
          Title | Rigging Trials Peer Review |  
        | Date | 12 August  2005 |  
        | Cognizant
          Engineer | Tom Brown |  
        | Responsible Line Manager | Brad Nelson |  
        | Review Board Chairperson | Larry Dudek |  
        | Review Board Members | Mike Cole, Mike Viola, Art 
		Brooks, Jim Chrzanowski, Steve Raftopoulos |  
        | Invitees | Wayne Reiersen, Hutch Neilson, 
	Erik Perry, Larry Dudek, Jerry Levine , Fred Dahlgren, Jim Chrzanowski, Mike 
	Cole, Brad Nelson, David Williamson, Paul Goranson, Mike Viola, Art Brooks, 
	Steve Raftopoulos, Ron Strykowsky, Frank Malinowski, Judy Malsbury, Greg 
	Pitonak, Jeff Makiel, |  
        | Attendees | Larry Dudek, Hutch Neilson, 
		Art Brooks, Bill Slavin, Judy Malsbury Mike Viola, Wayne Reiersen, Steve 
		Raftopoulos, Jim Chrzanowski, Mike Zarnstorff, Phil Heitzenroeder, Mike 
		Cole, Jim Lyons |  
        | Charge | 1. Does the block test 
			simulation adequately predict the ability to successfully move the 
			MC over the VV within the installation tolerances? 
			2. Can the laser screens 
			be fabricated and adequately located within some specified 
			tolerances to properly define the path of motion? Is there a better 
			approach? 3. If the MC is moved 
			in some manner that places it off the required path, is there a 
			method to find where it is, then retract and reposition it to be on 
			the correct path? 4. Technicians are 
			required to stabilize the MC (in close proximity to it) while it is 
			supported by the crane.  Are there any safety issues that need 
			to be addressed prior to making this decision? 5. Is there 
			additional work or documentation that should be done prior to making 
			this decision? |  
        | Design Review Material | 
        
        Announcement 
        
		Chits and Disposition Plan 
        
		Presentation 
        
		Summary of 
		Results |  
        | Review Board Report |  |  
        | Items Reviewed | 
    
     | Sat | Unsat | Comments |  
        | Appropriate requirements identified |  |   |  |  
        | Development plans and schedules |   |   |  |  
        | Regulatory compliance including USQD and NEPA |  |   |  |  
        | Disposition of CHITS from previous reviews |  |   |  |  
        | Cost 
          objectives |  |   |  |  
        | 
          Other 
          review objectives addressed 
          
          (Attachment 4 of ENG-033) |  |   |  |  
        | 
          Summary of Results |  |  
        | 
          Disposition 
          (check 
     one) |  Acceptable |  
        | 1 
		Acceptable pending resolution of concerns - 
    CHITS identified above must be resolved prior to installation. |  
        | 1Incomplete -
    Additional design 
    work is required prior to another design review. |  
        | 
          Cog Engineer Close-out 
          (check 
     when done) |  |  
        | 1  
    Action required by Disposition is complete |  |