Engineering > Design Review > WBS 186
Review Title Vacuum Vessel Prep Station FDR
Date 19 September  2005
Cognizant Engineer Tom Brown
Responsible Line Manager Brad Nelson
Review Board Chairperson Mike Cole
Review Board Members Brent Stratton, Paul Goranson, George Labik
Invitees Wayne Reiersen, Hutch Neilson, Jim Lyon, Dave Williamson, Jim Chrzanowski, Mike Viola, Dave Johnson, Fred Dahlgren, Jerry Levine, Brent Stratton, George Labik, Larry Dudek, Jeff Makiel, Gregory Pitonak, Judy Malsbury, Frank Malinowski, Brad Nelson, Paul Goranson
Attendees Mike Cole, Jim Chrzanowski, Jerry Levine, Judy Malsbury, Larry Dudek, Jeff Makiel, Lewis Morris, George Labik, Wayne Reiersen, Brent Stratton, Mike Viola
Charge 1. Have all the Chits been addressed?

2. Does the analysis adequately underpin the design and have they been checked?

3. Do the drawings define the design adequately to be used as the sole basis for fabrication and acceptance of the support fixture?

4. Has safety been adequately addressed in the design of the support fixture?

5. Can the support fixture, with Peer Review incorporated changes, be fabricated and installed within the budget and schedule identified in the project baseline?
Design Review Material

Announcement

Chits and Disposition Plan

Presentation

Drawings

Analysis Document

Review Report

Review Board Report
Items Reviewed

Sat Unsat

Comments

Appropriate requirements identified    
Development plans and schedules  
Regulatory compliance including USQD and NEPA    
Disposition of CHITS from previous reviews    
Cost objectives    

Other review objectives addressed

(Attachment 4 of ENG-033)

 

Summary of Results

Disposition

(check  one)

 1  Acceptable
 1 Acceptable pending resolution of concerns - CHITS identified above must be resolved prior to installation.
 1 Incomplete - Additional design work is required prior to another design review.

Cog Engineer Close-out

(check  when done)

 
 1 Action required by Disposition is complete