Summary
of SIT Meeting of 6/24/02From: Hutch Neilson [hneilson@pppl.gov]
Sent:
Monday, June 24, 2002 10:41 PM
To:
wreiersen@pppl.gov; mzarnstorff@pppl.gov; bsimmons@pppl.gov; Brad Nelson;
rstrykowsky@pppl.gov
Cc:
hneilson@mailserver.pppl.gov; John A. Schmidt; lyonjf@ornl.gov
Subject:
Summary of SIT Meeting of 6/24/02
Summary
of SIT Meeting of Monday, June 24, 2002.
Discussion
Material: Engineering Issues
(Reiersen)
Progress
along the critical-path schedule:
Modifying
the Coil Design to Increase Plasma-Wall Clearance (Mike):
Two new
coil designs have been posted recently. Their aim is to increase plasma-wall
clearance and reduce coil currents. NBI access is potentially an issue.
Action:
Brad, check with Dave Williamson about NBI access on the new designs.
The
PIES group is in the process of healing the new coil designs. The healing
effort is going well.
A third
case (still lower currents) is under development. It would depart from the CDR
winding surface, however, which is a concern.
Modifying
the Configuration to Increase Plasma-Wall Clearance (Brad)
Still awaiting
delivery of Poincaré points from Mioduszewski.
The
internal trim coils and rf launchers need to be updated to the latest
configuration. Majeski and Cole are talking.
WBS 1
Planning. What is the schedule?
Tasks
have started. Plan for remainder of FY-02 is being reviewed by the responsible
engineers. Goal is to complete the planning by next Monday, July 1.
WBS 3
Planning.
This
needs to get higher priority in order to support the definition of interfaces
important to design of the stellarator core. If necessary, the effort can be
broadened.
ACTION:
Wayne discuss with Dave Johnson.
WBS 8
Planning.
There
is much to do in the remainder of the Fiscal Year. Establishing baselines,
implementing project control system, change control, interface control, plans
for FY-03.
ACTION:
Wayne, Hutch, Bob, Ron
Coil
Protection System. What is the Plan?
Requirements
will be driven by WBS 1 needs.
Brad
needs to know what is reasonable and what sensors are needed.
ACTION:
Wayne obtain documentation on NSTX system from Marsala and Schneider.
Magnetic
Diagnostics
Transfer
of magnetic diagnostics to WBS 1 was reconsidered.
It was
decided that that they should be moved back to WBS 3, for the reason that the
magnetic diagnostics should be managed like other diagnostics. Engineering is responsible for ensuring that
interfaces (e.g., with the stellarator core) are properly defined and managed.
Project physics is responsible for setting requirements; physics has identified
Ed Lazarus to define requirements for equilibrium reconstruction. An individual
must be identified to be responsible for the design. System requirements and
interfaces must be defined in FY03.
Action:
Mike discuss with Jim Lyon concerning possible ORNL candidates to lead or
support.
Action:
Hutch discuss with Dave Johnson concerning possible PPPL candidates to lead or
support.
Integrated
System Testing
Transfer
of Integrated System Testing to Construction was reconsidered.
Another
possibility is to view it as a transition to the operations phase. This would
argue for having Integrated Systems Testing as a separate WBS, e.g. WBS 9.
ACTION:
Wayne to make a recommendation next week.
CDR
Recommendations
Wayne
is collecting comments on the proposed CDR recommendation responses. Plan is to
develop disposition plan sufficient for CD-1, by June 28.
ACTION:
Hutch incorporate comments and combine duplicate recommendations.
Meetings
Monthly
project meetings are being considered by engineering. It would function as a
project-wide integration meeting. It was suggested that it might displace the
weekly WBS 1 meeting one week out of the month. Other meetings are the Monday
SIT meetings, the Wednesday WBS 1 meetings, and the Thursday physics meetings.
Next
SIT Meeting: Monday, July 1, 2002, 11:00 a.m. EDT. Usual arrangements.
Agenda:
Critical-path tasks; WBS 1 plans for remainder of FY; action items.
Please
bring any corrections to my attention.
Thanks
to all,
Hutch