ECP-027

RFD-12-002

  • ECP Cover Page & Description (Part I) - Approved March 24, 2005

    • RFD-12-002-R1

    • ECN #4972

    • Action Items

      • Issue Contract Addendum by 4/24/05

      • Prepare ECN (#4972 Assigned) to identify drawings that need to be revised - See Above

      • Revise pdf drawings RFD-12-002 by 3/24/2005 - at next update of ProE models and drawings, incorporate the note into the ProE models and drawings

      • Revise CSPEC by 4/24/05

 