NCSX Web Pages  

NCSX FTP Sites  

Project FTP Server | Supplier FTP Server

Navigation Trail  

Engineering > Change Control > ECP Status List
   
 ECP Forms
   
ECP Number ECN? RFD? Title Date Approved or Disapproved Impacted WBS Elements Type of Impact (Tech, Cost, or Schedule)
040            
060     NCSX Closeout 11/13/2008 All Technical, Cost, & Schedule
059     VV Pressure Test Reqmts 2/25/2008 18 Technical
058     Update of VV & Station 1 FPA Requirement Documents 11/5/2007 12 & 18 Technical
057     Update of TF Coil Assembly CSPEC 9/18/2007 131 Technical
056    

Update of Plasma Spray Coating for Prototype and Production Modular Coil Shims

8/9/2007 142 Technical
055     Updated Requirements 8/3/2007 WBS 1, 4, & 7 Technical
054     FY2007 Rebaselining     Cancelled
053     Near Term Replanning 2/9/2007 All Technical, Cost, & Schedule
052    

FY2007 Replanning, Risk Retirement, and Estimate Updates

11/1/2006 All Cost & Schedule
051 5178R1   Update of TF Coil Assembly CSPEC (NCSX-CSPEC-131-01) 12/07/2006 131 Editorial Update to Reflect Latest Drawing List
050     WBS 3 Internal Reprogramming 7/27/2006 3 Cost
049     Risk Retirement - FY2006 Scope Completions 7/31/2006 14, 17, & 4 Cost
048     Update of GRD (Rev 4) 7/14/2006 All Technical & Editorial
047   RFDs 14-014 thru 14-022 Update of MCWF CSPEC (Rev 12) 7/18/2006 14 Technical
046     Update of TF Coil Assembly Requirements 4/13/2006 14 Technical
045    

May 2006 PMB Update

6/13/2006 14 Technical, Cost & Schedule
044

5067

5082

12-006, 14-009, & 12-010, 12-012, 12-013, 12-014& 12-015 Update of VVSA CSPEC   12 Technical
043     March 2006 PMB Updated 3/27/2006 14, 18 Cost & Schedule
042 5045, 5059R2, 5064R1 & 5066 14-010, 14-011, 14-012 & 14-013 MCWF Machining Improvements 2/9/2006 14 Technical (Cost and Schedule will be in ECP-043)
041     Update of PMB - December 2005

ECP Rescinded 3/6/2006

12, 18 Schedule
040     Updated of Modular Coil SRD 12/2/2005 14 Technical
039     PMB Update 11/9/2005 12, 13, 14, 17, 18, 3, 4, 7, 8 Cost & Schedule
038 5016

5026

14-005, 14-006, 14-008, 14-009R1 MCWF Technical Requirements Update 11/3/2005 13 Technical
037     Revision 3 to the GRD 9/9/2005 13, 14, & 4 Technical
036     Risk Retirement, Budget Reallocation, Correction of Data Error,  and New Work 8/9/2005 12, 14, & 19 Cost & Schedule
035 X   Changes to MCWF Technical Requirements 8/5/2005 14 Technical
034     Vacuum Vessel Trinos Flanges 7/11/2005 12 Cost
033-R1 X X Revision 1 to MCWF Technical Reqmts 7/19/2005 14 Technical & Cost
032   X RFD-14-006 - permit 2.5" and 3.5" pipe to be manufactured from ASTM 625 plate 5/27/2005 12 Technical
031     DOE Directed Rebaseline 8/10/2005 All Cost & Schedule
030     Planning Changes for Risk Management 5/4/2005 All Technical, Cost, & Schedule
029     Retirement of Risks for VVSA Forming Dies and Twisted Racetrack Assembly 4/21/2005 12 & 14 Cost
028   X RFD-14-001 - Relocation of Pattern/Casting ID Number 3/30/2005 14 Technical
027 X X RFD-12-002R1 - Substitution of Sch10 Pipe for Sch40 Pipe for the 2.5" Pipe 3/24/2005 12 Technical
026 X   MCWF Fast Response 3/14/2005 141 Technical
025   X RFD-12-001 - Manufacture of the 6", 8" and 10" Pipe from ASTM 625 Plate 3/10/2005 12 Technical
024     Miscellaneous Rescheduling and Contingency Draw for Added and Re-Estimated Scope 3/7/2005 12, 13, 81 & 82 Technical, Cost, & Schedule
023     MCWF Minimum Mechanical Properties 2/17/2005 141 Technical
022 R1 X

Y

  TRC Design Updates R1 - 2/3/2005 142 Technical, Cost, & Schedule
021     Job Close-Out & Contingency Drawdown 1/31/2005

12, 141, 142, & 84

Cost & Schedule
020 X   Resolution of MCWF Questions (Dec-2004) 1/14/2005

141

Technical
019 X

Y

  VVSA Contract Addenda 3-1 though 3-3 1/25/2005

121

Technical
018     FY005 Replanning Baseline 11/19/2004 12, 14, 15, 18, 19, 3, 4, 5, & 7 Technical, Cost, & Schedule
017R1 X   VVSA Inner Support Bosses 11/9/2004 121 Technical
016R1     Reprogramming for FY2004 Closeout 11/9/2004 121, 133, 141, 142, 144, 19, 21, 432, 612, 614, & 82 Technical, Cost, & Schedule
015 X   Final Technical Scope of MCWF 9/17/2004 141 Technical
014     CD-3 Replanning 9/20/2004 12, 14, 187, 25, 3, 4, 5, 62, 64, 81, 82, 84, & 85 Technical, Cost, & Schedule
013 X   Modifications to VV Joint R&D Seals and End Pieces 7/30/2004 121 Technical &  Cost
012 X   MCWF Lead Block and Support Modifications 7/30/2004 141 Technical
011     Rebaseline for Modular Coil WAFs 7/28//2004 14 Cost & Schedule
010 X   Prototype Winding Form Poloidal Break Geometry 6/28//2004 141 Technical
009     Reprogramming 7/8/2004 141, 142, & 185 Technical, Cost, & Schedule
008     Update of the Technical Baseine to Reflect the VVSA and MCWF FDR Design Configuration 6/23/2004 121, 141, & 185 Technical, Cost, & Schedule
007 X   Twisted Racetrack VPI Groove Depth 4/28/2004 141 Technical
006     Updated Cost and Schedule Estimate for Design and R&D 4/29/2004 121, 13, 141, 144, & 144 Technical, Cost, & Schedule
005     Revised Estimates fro Design, R&D, and Tooling 3/15/2004 12, 14, 18, 2, 3, 4, 5, 6, 7, & 8 Technical, Cost, & Schedule
004     CD-2 Cost and Schedule Baseline 2/28//2004 12, 14, 16, 18, 2, 3, 4, 5, 6, 7, & 8 Technical, Cost, & Schedule
003     FY2004 Management Reserve Distributions 1/20/2004 Various WBS Elements Cost
002     Change in MCWF Design 11/18/2003 141 Technical
001     Revision 1 to the General Requirements Document 1/23/2004 1, 2, 3, 4, 5, 6, & 7 Technical

 

Privacy and Security Notice

Please forward comments and questions to the bsimmons@pppl.gov