Title |
Document Number |
Modular Coil Plans |
Modular Coil Manufacturing,
Inspection, Test , and Quality Assurance Plan |
NCSX-MITQA-142-00
|
Modular Coil Winding Dimensional
Control Plan |
NCSX-PLAN-MCWDC-00 |
Modular Coil
Manufacturing Procedures |
Modular Coil
Fabrication-Winding Form Preparation Activities |
D-NCSX-MCF-001-03
(ORIGINAL IN OPS CENTER)
|
Modular Coil
Fabrication-Winding Station Activities |
D-NCSX-MCF-002-02
(ORIGINAL IN OPS CENTER) |
Modular Coil
Fabrication-VPI/Autoclave Activities |
D-NCSX-MCF-003-03
(ORIGINAL IN OPS CENTER) |
|
D-NCSX-MCF-004-01
(ORIGINAL IN OPS CENTER) |
Dimensional Control and Metrology for the NCSX Modular Coils
|
D-NCSX-MCF-005-02
(ORIGINAL IN OPS CENTER) |
Modular Coils Operating Procedures |
Modular Coil Manufacturing
Facility Autoclave Operating Procedure |
D-NCSX-OP-G-162-01
(ORIGINAL IN OPS CENTER) |
Modular Emergency Response Procedures |
Modular Coil Manufacturing
Facility Emergency Response Procedure |
D-NCSX-OP-EO-41-00
(ORIGINAL IN OPS CENTER) |
Modular Lift Procedures |
Modular Coil Winding Form Lift Procedure |
D-L-NCSX-983-01
(ORIGINAL IN OPS CENTER) |
Modular Coil Lift Procedure |
D-L-NCSX-984-00
(ORIGINAL IN OPS CENTER) |
Finished Modular Coil Winding Form Lift Procedure |
D-L-NCSX-996-00
(ORIGINAL IN OPS CENTER) |
Modular Repair Procedures |
Modular Coil Lead Repair - Part 1 Exploration |
D-NCSX-RP-STEL-057-00
(ORIGINAL IN OPS CENTER) |
Modular Coil Lead Repair - Part 2 Repair |
D-NCSX-RO-STEL-058-00
(Draft in Review) |
Modular Access Procedures |
Personnel Access of the NCSX Autoclave |
D-NCSX-OP-763-00
(ORIGINAL IN OPS CENTER) |
|
Toroidal Field Coils Plans and Procedures
|
Title |
Document Number |
Toroidal Field Coil Plans |
Toroidal Coil Manufacturing,
Inspection, Test , and Quality Assurance Plan |
NCSX-MITQA-131-01-00
(Approved) |
|
Field Period Assembly
Plans and Procedures
|
Field Period Assembly Plans |
Field Period Assembly Plan |
NCSX-PLAN-FPA-00-dA |
Field Period Assembly Manufacturing,
Inspection, Test , and Quality Assurance Plan |
NCSX-MIT/QA-185-01-00 |
Station 1 Field Period
Assembly Sequence Plan |
NCSX-PLAN-FPA1SEQ-00 |
Field Period Assembly Station 1
Dimensional
Control Plan |
NCSX-PLAN-FPA1DC-00
|
Field
Period Assembly Procedures |
Field Period Assembly
Component Receipt Inspection |
D-NCSX-FPA-QA1-00
(ORIGINAL IN OPS CENTER) |
Field Period Assembly Station
One |
D-NCSX-FPA-001-00
(ORIGINAL IN OPS CENTER) |
Field Period Assembly Lift Procedures |
VVSA Lift Procedure |
D-L-NCSX-997-00
(ORIGINAL IN OPS CENTER) |