NCSX Basis of Estimate
(2007 Rebaseline)
|
WBS |
Job |
Job Title |
12 - Vacuum Vessel Systems |
1204 |
Vacuum Vessel Procurements (Non-VVSA) |
13 - Conventional Coils |
1302/1352 |
PF Coil Design (1302)
PF Coil Procurements (1352) |
|
1353 |
Central Solenoid Procurement |
|
1354 |
Trim Coil Design & Procurement |
|
1355 |
Conventional Coils I&C |
|
1361 |
TF Coil Fabrication |
14 - Modular Coils |
1408/1451/1459 |
Modular Coil Winding Supplies (1408)
Modular Coil Winding Operations (1451)
Modular Coil Fabrication Punch List Items (1459) |
|
1416 |
Modular Coil Type A&B Design |
|
1421 |
Modular Coil Interface Design |
|
1431 |
Modular Coil Interface Hardware |
15 - Coil Support Structures |
1501/1550 |
Coil Structures Design (1501)
Coil Structures Procurement (1550) |
16 - Coil Services |
1601-161
1601-162
1601-163 |
LN2 Distribution System (1601-161)
Coil Electrical Leads (1601-162)
Coil Protection System Interfaces (1601-163) |
17 - Cryostat & Base Support Structure |
1701/1751 |
Cryostat Design (1701)
Cryostat Procurements (1751) |
|
1702/1752 |
Base Support Structure Design (1702)
Base Support Structure Procurements (1752) |
18 - Field Period Assembly |
1802/1810/1815 |
FPA Oversight & Support (1802)
FPA Operations - Stations 1, 2 & 3 (1810)
FPA Operations - Station 5 (1815) |
|
1803/1805 |
FPA Tooling Design & Constructibility (1803)
FPA Hardware Procurements (1805) |
|
1806 |
FPA Specifications & Drawings |
19 - Stellarator Core Mgmt & Integration |
1901 |
Stellarator Core Management & Integration |
21 - Fueling Systems |
2101 |
Gas Fueling Systems |
22 - Torus Vacuum Pumping Systems |
2202 |
Vacuum Pumping Systems |
3 - Diagnostic Systems |
3101 |
Magnetic Diagnostic Systems |
|
3601 |
Edge & Divertor Diagnostic Systems |
|
3801 |
Electron Beam Mapping Systems |
|
3901 |
Diagnostic Integration |
4 - Electrical Power Systems |
4101 |
AC Power Systems |
|
4301 |
DC Power Systems |
|
4401 |
Control & Protection Systems |
|
4501 |
Power Systems Design & Integration |
5 - Central Controls and Computing |
5101 |
Network & Fiber Optic Infrastructure Systems |
|
5201 |
Central Instrumentation & Control Systems |
|
5301 |
Data Acquisition & Facility Computing Systems |
|
5401 |
Facility Timing & Synchronization Systems |
|
5501 |
Real Time Plasma Control Systems |
|
5601 |
Central Safety Interlock Systems |
|
5801 |
Central I&C Management & Integration |
6 - Facility Systems |
6101 |
Cooling Water Systems |
|
6201 |
Cryogenic Systems |
|
6301 |
Utility Systems |
|
6401 |
Bakeout Systems |
7 - Test Cell Prep & Machine Assembly |
7301 |
Platform Design & Fabrication |
|
7401/7451 |
Machine Assembly Planning & Oversight |
|
7501/7503 |
Construction Support (7501)
Machine Assembly Operations (7503) |
|
7601 |
Machine AssemblyTooling Design & Fabrication |
81 - Project Management & Integration |
8101/8102/8998 |
Project Management @ PPPL (8101)
Project Management @ ORNL (8102)
PPPL Direct Allocations (8998) |
82 - Project Engineering |
8202 |
Engineering Management & Systems Engineering |
|
8203 |
Design Integration |
|
8204 |
Systems Analysis & Technical Assurance |
|
8205 |
Dimensional Control Coordination |
|
8215 |
Plant Design |
85 - Integrated Systems Testing |
8501 |
Integrated Systems Testing |