Legend
Date
|
Conducted
|
Date
|
Closed
|
[Note]
|
See
note below table
|
|
Please
click on dates underlined in table below to access design review
material...
WBS
|
Description
|
Peer
Review or CDR
|
PDR
|
FDR
|
Other
|
12
|
Vacuum
Vessel Systems
|
|
10/6/03
|
9/16/05
|
|
|
Vacuum Vessel SRD |
4/1/04 |
|
|
|
|
VV Interfaces |
12/01/05 |
|
|
|
|
Clamp Design |
|
|
3/23/06 |
|
121
|
Assembly
|
|
|
|
|
|
VVSA FDR |
|
|
5/19/04 |
|
|
VV Port
Configuration
|
1/29/04 |
|
|
|
|
Prototype
Vacuum Vessel Segment (PVVS)
|
|
|
7/8/03
|
|
|
VVSA Product Spec
Review |
4/8/04 |
|
|
|
|
VV Weld Joint R&D Plan
|
3/25/04 |
|
|
|
|
VVSA SOW Document
Review |
4/14/04
|
|
|
|
|
VV Structural Design
Analysis |
4/22/04 |
|
|
|
|
VV SXR Spacer
Modifications |
|
|
2/14/06 |
|
122
|
Thermal
Insulation
|
|
|
7/31/06
|
|
123
|
Heating
and Cooling Distribution System
|
|
|
|
|
|
VV Coolant Hose Design
& Thermal Hydraulic |
|
|
4/4/06 |
|
|
VV Heating Tape &
Thermocouples |
|
|
4/27/06 |
|
124
|
Supports
|
|
|
5/5/05 |
|
|
Lateral Supports and
Manned Access Port |
|
|
11/17/05
|
|
125
|
Local
I&C
|
|
|
|
|
Notes:
[1]
Not in MIE Project, but design reviews will be required.
[2]