NCSX Web Pages  

Project | Management | Physics | Procurement | Manufacturing

NCSX FTP Sites  

Project FTP Server | Supplier FTP Server

Navigation Trail  

Engineering > NCSX Management Plans

NCSX Management Plans

NOTE:  THESE SIGNED PLANS ARE PROTECTED TO PRECLUDE UNAUTHORIZED CHANGES.  IF YOU NEED TO PRINT THESE DOCUMENTS AS UNCONTROLLED COPY, PLEASE USE THE PASSWORD "ncsx" (ALL LOWER CASE WITHOUT THE QUOTES).

Name of Plan

Currently Approved Revision

  Drafts/Revisions in Process

Peer Reviews of Initial Issue

Plans Approved by DOE

     
 Acquisition Execution Plan (AEP) Revision 0    
Project Execution Plan (PEP)

Revision 3

Approval Letter (Aug 11, 2005)

Revision 4-G3  (April 2008)

 

Plans Approved by Project

     
Systems Engineering Management Plan (SEMP)

Revision 0

 

5/15/2003
Quality Assurance Plan (QAP)

Revision 1

 

11/1/2002
Configuration Management Plan (CMP) Revision 2   12/17/2002
Data Management Plan (DMP) Revision 4   3/31/2003
Document and Records Plan (DOC)

Revision 4

  3/14/2003
Interface Control Management Plan (ICMP)

Revision 1

 

12/19/2002
Reliability, Availability, and Maintainability Plan (RAM)

Revision 0

 

 
Test and Evaluation Plan (TEP)   Draft D (May 2006)  
Risk Management Plan (RMP)

Revision 1

 

 
Safe Startup and Control Plan (SSU) Revision 0

Revision 1 Draft (March 2008)

 
CD-4 Start Up Plan

CD-4 Start Up Chart

 

Revision 0 Draft (March 2008)

Revision 0 Draft (march 2008)

 
Safety Analysis Document (SAD)  

Revision 0 Draft (March 2008)

 
Experimental Plan (EP)

 

 Version 3 - Being Reviewed and Updated

 
Radiation Safety Plan (RSP)

 

NOT YET DRAFTED

 
Training Plan (TRNG)

Revision 2

 

 

Privacy and Security Notice

Please forward comments and questions to the bsimmons@pppl.gov