| Review
          Title | Twisted Racetrack Coil 
		FDR | 
      
        | Date | 15 October 2004 | 
      
        | Cognizant
          Engineer | Dave Williamson | 
      
        | Responsible Line Manager | Wayne Reiersen | 
      
        | Review Board Chairperson | Larry Dudek | 
      
        | Review Board Members | Phil Heitzenroeder, Mike 
		Cole, Geoff Gettelfinger, Mike Kalish, Tom Brown, Brent Stratton, Art 
		Brooks | 
      
        | Invited Attendees | Jerry Levine, Judy Malsbury, 
		Hutch Neilson, Mike Zarnstorff, Richard Hawryluk, Mike Williams | 
      
        | Attendees | Larry Dudek, Wayne Reiersen, 
		Tom Brown, Art Brooks, Brent Stratton, Judy Malsbury, Mike Kalish, Phil 
		Heitzenroeder, Jerry Levine, Bill Slavin, Leif Dietrich, Ray Camp, Dori 
		Barnes, Jim Chrzanowski, Geoff Gettelfinger, Don Hinman | 
      
        | Charge | 
			
			Have the TRC 
			requirements been appropriately defined?  Have the means to verify 
			that the requirements have been met been identified?
			Has the design been 
			adequately defined for component fabrication and coil assembly?
			Is the assembly 
			procedure been adequately defined in the MIT/QA plan and supporting 
			procedures?  Does the assembly procedure appear reasonable and 
			consistent with the coil design?
			Does the assembly 
			procedure and metrology plan (including measurement and 
			compensation) appear suitable to achieve the tight tolerance 
			requirement for control of the current center?
			Do the planned safety 
			controls appear adequate?
			Is the test plan adequately defined?  Have instrumentation 
			requirements for the TRC been defined consistent with the test plan?   
			 | 
      
        | Design Review Material | 
        
        Announcement 
        
        Twisted Racetrack Coil Presentation 
        TRC Testing 3 
		Presentation 
        
		TRC Product Specification 
        
		Drawing Package 
        
		Design Viewgraphs 
        
        Chits and Disposition Plan | 
      
        | Review Board Report |  | 
      
        | Items Reviewed | 
    
     | Sat | Unsat | Comments | 
      
        | Appropriate requirements identified |  |   |  | 
      
        | Development plans and schedules |  |   |  | 
      
        | Regulatory compliance including USQD and NEPA |  |   |  | 
      
        | Disposition of CHITS from previous reviews |   |   | Not applicable | 
      
        | Cost 
          objectives |   |   |  | 
      
        | 
          Other 
          review objectives addressed 
          
          (Attachment 4 of ENG-033) |   |   |  | 
      
        | 
          Summary of Results | 
    
     | 
      
        | 
          Disposition 
          (check 
     one) | 1Acceptable | 
      
        |  Acceptable pending resolution of concerns - 
    CHITS identified above must be resolved  prior to installation. | 
      
        | 1Incomplete -
    Additional design 
    work is required prior to another design review. | 
      
        | 
          Cog Engineer Close-out 
          (check 
     when done) |  | 
      
        | 1  
    Action required by Disposition is complete |