Review
Title |
PF Coils FDR |
Date |
20 February 2008 |
Cognizant
Engineer |
Jim Chrzanowski |
Responsible Line Manager |
Phil Heitzenroeder |
Review Board Chairperson |
Al von Halle |
Review Board Members |
Ted Hunter, Charles
Neumeyer, Raki Ramakrishnan, Wayne Reiersen, Al von Halle |
Invitees |
Larry Dudek, Jeff Makiel,
Jerry Levine, Judy Malsbury, Jim Chrzanowski, Al von Halle, Charles
Neumeyer, Ted Hunter, Raki Ramakrishnan, Wayne Reiersen, Don Rej, Hutch
Neilson, Jeff Harris, Frank Malinowski, Tom Meighan, Larry Sutton, Joe
Rushinski, Fred Dahlgren, Mike Cole, Art Brooks, Mike Kalish, Bob
Simmons, Robert Parsells |
Attendees |
Jerry Levine, Frank
Malinowski, Tom Meighan, Larry Sutton, Hutch Neilson, Joe Rushinski,
Larry Dudek, Fred Dahlgren, Mike Cole, Art Brooks, Jeff Makiel, Don Rej,
Mike Kalish, Bob Simmons, Bob Parsells, Jeff Harris |
Charge |
The charge
to the review committee is: 1)
Are the requirements defined? What is the proposed design?
2) Is the analysis consistent with the
proposed design?
3) Are fabrication documents
(drawings, specifications) complete?
4) Are there satisfactory fabrication
plans?
5) Have prior design review chits been
addressed?
6) Have all technical, cost/schedule,
and safety risks been addressed? |
Design Review Material |
Announcement
Chits and Disposition
Presentation
Specification
Drawings
se132-060
se132-040
se132-050
|
Review Board Report |
|
Items Reviewed |
|
Sat |
Unsat |
Comments |
Appropriate requirements identified
|
X |
|
SRD approved and posted |
Development plans and schedules |
X
|
|
|
Regulatory compliance including USQD and NEPA |
|
|
Not covered in this review |
Disposition of CHITS from previous reviews |
X
|
|
PDR Chits/resolutions posted |
Cost
objectives |
X
|
|
|
Other
review objectives addressed
(Attachment 4 of ENG-033) |
|
|
|
Summary of Results
|
The design of the
NCSX PF4, PF5 and PF6 coils was reviewed on 2/20/08. Detailed aspects of the
proposed coil construction were presented including all physical
dimensions, and specifications for epoxy, insulating materials, and
conductors (common to all three coils). The expected mechanical and
electrical performance of the completed coils was reviewed, and a
summary of analysis and testing needed to develop a good fabrication
plan was available. Drawings for all three coils have been completed
and were available for this review, but questions on several design
details remained unanswered. Chit were generated and the review
committee decided to reconvene after the final approval of the System
Requirements Document, and the posted availability of documented (and
reviewed) support analysis.
The review committee
again met on 3/4/08 to review the chits from the FDR in the light of the
now finalized System Requirement Document. The committee concurred that
the designed package for the PF coils is ready to go out for
procurement/fabrication. It was recognized, however, that
interfacing systems have not reached final design, and the majority of
the chits written during this review are concerned with details of these
interfaces. |
Disposition
(check
one) |
1 Acceptable |
Acceptable pending resolution of concerns -
CHITS identified above must be resolved prior to installation. |
1 Incomplete -
Additional design
work is required prior to another design review.
|
Cog Engineer Close-out
(check
when done) |
|
1
Action required by Disposition is complete |
|