RFD Number |
Associated ECP Number |
Title |
Date Approved or
Disapproved |
RFD Status |
|
|
|
|
|
WBS
12 Requests for Deviation |
|
|
12-024 |
|
Remove trimming
of VVSA Seal Plates |
10/22/2007 |
Approved.
"Stamp" added. |
12-023 |
|
Rearrangement of VV1
Cooling Tubes |
4/25/2007 |
Approved.
"Stamp" added. |
12-022 |
|
Replacement of
Scrapped VVSA #3 Flanges on the Spacer Assembly |
5/22/2006 |
Approved. |
12-021 |
|
VVSA Flange Seal
Holes |
4/28/2006 |
Approved.
"Stamp" added. |
12-020 |
|
NCSX VVSA Flange Seal
O-Ring Groove |
4/24/2006 |
Approved.
ECN 5123 added as note. |
12-019R1 |
|
Welp Prep on Port
Extensions |
4/12/2006 |
Approved.
ECN 5111 added as note. |
12-018 |
|
Leak Check Tube and
Block Location |
4/11/2006 |
Approved.
ECN 5118 added as note. |
12-017 |
|
Port Attachment Weld
Deviation Request |
4/21/2006 |
Approved.
ECN 5121 added as note. |
12-016 |
|
NCSX VVSA Flange
Seal Weld |
4/5/2006 |
Approved.
ECN 5115 added as note. CSPEC needs to be updated. |
12-015 |
|
NCSX VVSA Spacer
Machining |
3/1/2006 |
Approved. Modify
CSPEC by 3/7/2006.
ECN 5114 added as note. |
12-014 |
|
Elimination of
Weld Relief on End Covers |
2/21/2006 |
Approved. Modify
CSPEC by 3/7/2006.
ECN 5082 added as note. |
12-013 |
|
Deletion of NCSX VVSA
Bake Out and Thermal Cycling for 2nd and 3rd
120º
VVSA Segments |
2/17/2006 |
Approved. Modify
CSPEC by 3/7/2006 |
12-012 |
|
Waiver of NCSX VVSA
Third
Thermal Cycle for 1st 120º
VVSA Segment |
2/16/2006 |
Approved. Modify
CSPEC by 3/7/2006 |
12-011 |
|
Relax tolerances on
Manifold Bends |
2/14/2006 |
Approved. |
12-010 |
|
NCSX NB Seal /
Cover Plate Assembly |
1/20/2006 |
Approved. Drawing to
be modified to change other VVSA segment NB seal/cover plate
assemblies.
ECN 5117 added as note. |
12-009 |
|
NCSX Vessel Port
Manufacture |
10/24/2005 |
Approved. Option 1
selected.
ECN 5113 added as note. |
12-008 |
|
Change in Seal and
Port Cover Material |
10/20/2005 |
Disapproved - Inconel
required. Howerver, MTM is still free to suggest an alternate
material for the plate if they can find one that is compatible with
bakeout (i.e., acceptable thermal stresses). |
12-007 |
|
NCSX Vessel Port
Pre-Assembly and Blank-Off for Vacuum Testing |
8/22/2005 |
Disapproved - leak
checking ok, but PPPL needs all the blank off flanges for testing at
PPPL. |
12-006 |
032 |
NCSX Vessel Port
Manufacture |
5/27/2005 |
Authorization to
manufacture 2.5" pipe and 3.5" pipe from ASTM 625 plate. |
12-005 |
N/A |
NCSX Vessel Port
Manufacture |
5/18/2005 |
DISAPPROVED
-
Search for more Sch40 pipe - Project will evaluate Sch10 splicing
strategy. |
12-004 |
N/A |
VVSA Leak Check
Tube/Block Weld |
4/4/2005 |
It is permissible to
replace the weld with a braze joint using a silver free braze
material (Nicrobraz).
ECN 5109 added as note. |
12-003 |
N/A |
VVSA Tube Clip
Thickness |
4/4/2005 |
The use of any gauge
in the range of 0.01 to 0.02 will be acceptable to the Laboratory
provided it is Inconel 625 alloy, and is found to perform adequately
by the vendor.
ECN 5110 added as note. |
12-002R1 |
027 |
RFD-12-002,
Substitution of Schedule 10 for Schedule 40 Piping |
3/24/2005 |
Incorporated in Rev 5
of NCSX-CSPEC-121-02.
ECN 4972 added as note. |
12-001 |
025 |
RFD-12-001 - Approval
to use ASTM B705 and ASTM B443 for Manufacture of Piping from Plate |
3/10/2005 |
Incorporated in Rev 5
of NCSX-CSPEC-121-02 |