The NCSX Closeout Notes are intended to document the status of each job to provide final status of the job when the NCSX Project was cancelled. The closeout notes should be addressed to the appropriate RLM (or Mike Cole in the case of ORNL jobs). Only those jobs in process and/or planned at time of Project cancellation will be will require closeout notes. The following information is provided below to guide each Job Manager in preparing a closeout note that is consistent with all the other closeout notes in format.

Text Box: Not done Yet
Text Box: Done

 

 

 

Color Keys: 

        

Text Box: Completed Before Cancellation  or No Closeout Note Needed
                                       
 
 

 

 

                            

WBS/Job/Title/Closeout Note Link

Job Manager

Status at Closeout
       
WBS 12 - Vacuum Vessel

 

 

  1201 - Vacuum Vessel Preliminary Design Goranson Completed (Oct 2003)
  1202 - Vacuum Vessel R&D Goranson Completed (Sept 2005)
  1203 - Vacuum Vessel Final Design Goranson Completed (Aug 2006)
  1204 - Vacuum Vessel System Procurements (Non-VVSA) Dudek In Process at Time of Cancellation
  1206 - Vacuum Vessel Field Weld Joint Goranson Completed (Sept 2005)
  1250 - Vacuum Vessel Fabrication Viola Completed (Sept 2006)
  1260 - Neutral Beam Transition Duct Cole In Process at Time of Cancellation
  1270 - Heater Control System Goranson In Process at Time of Cancellation
WBS 13 - Conventional Coils    
  TF Coils    
    1301 - TF Coil Design Kalish Completed (April 2006)
    1350 - TF Coil Fabrication Preparations Chrzanowski Cancelled when Decision Made for Industry to Fabricate (Mar 2006)
    1351 - TF Coil Fabrication Supplies Kalish Completed (Oct 2006)
    1361 - TF Coil Fabrication Kalish/Meighan Will Complete as Part of Closeout
  PF Coils    
    1302/1352 - PF Coil Design/PF Coil Fabrication Chrzanowski Design Completed & Fab Contract about to be awarded at Time of Cancellation
  Coil Support Structures    
    1353 - CS Structures Design Dahlgren Cancelled when Decision Made to Use NSTX PF1a (Aug 2006)
  Trim Coils    
  1354 - Trim Coil Design & Procurement Kalish In Process at Time of Cancellation
  Conventional Coil I&C    
  1355 - Trim Coil Design & Procurement Cole In Process at Time of Cancellation
WBS 14 - Modular Coils    
  1401 - Modular Coil Preliminary Design Williamson Completed (Sept 2005)
  1402 - Modular Coil Analyses Williamson Completed (Sept 2005)
  1403 - Modular Coil Final Design Williamson Completed (April 2006)
  1404 - MCWF R&D & First Production Casting Chrzanowski Completed (Sept 2005)
  1405 - Modular Coil Winding R&D Preparations Chrzanowski Completed (Sept 2005)
  1406 - Modular Coil Winding R&D Chrzanowski Completed (Mar 2006)
  1407 - Modular Coil Winding Facility  Chrzanowski Completed (Mar 2006)
 

1408/1451/1459 - Modular Coil Manufacturing

  • Job 1408 - Modular Coil Winding Facility

  • Job 1451 - Modular Coil Winging Operations

  • Job 1459 - Modular Coil Fab Punch List Items

Chrzanowski Completed as Part of Closeout
  1409 - Coil Test Stand Gettelfinger Completed (July 2006)
  1410 - Modular Coil Twisted Racetrack Fabrication Chrzanowski Completed (Mar 2006)
  1411 - MCWF Fabrication Heitzenroeder Completed (June 2007)
  1412 - Complete Winding Facilities Chrzanowski Completed (Mar 2006)
  1413 - MCWF Fracture Analyses Williamson Completed (Mar 2006)
  1414 - Coil Testing Gettelfinger Completed (July 2006)
  1416 - Modular Coil Type A/B Design Cole In Process at Time of Cancellation
  1419 - Winding Facilities Modifications Chrzanowski Completed (Jan 2007)
  1421 - Modular Coil Interface Design @ ORNL  

Cole

Williamson

In Process at Time of Cancellation
  1429 - Modular Coil Interface R&D @ PPPL Dudek In Process at Time of Cancellation
  1431/1421 - Modular Coil Interface Hardware Dudek In Process at Time of Cancellation
  1460 - Modular Coil Third Winding Fixture Chrzanowski In Process at Time of Cancellation
WBS 15 Coil Support Structures    
  1501 - Coil Support Structures Dahlgren Will Complete as Part of Closeout
  1550 - Coil Support Structures Procurements Chrzanowski Cancelled when Project Cancelled
WBS 16 - Coil Services    
  1601-161 - LN2 Distribution Systems Goranson In Process at Time of Cancellation
  1601-162 - Coil Electrical Leads Goranson In Process at Time of Cancellation
  1601-163 - Coil Protection System Interfaces Harris In Process at Time of Cancellation
WBS 17 - Cryostat & Base Support Structure    
  Cryostat    
    1701/1751 - Cryostat Design/Procurements Raftopoulos In Process at Time of Cancellation. No procurement activities had commenced.
  Base Support Structure    
    1702 - Base Support Structure Design Dahlgren In Process at Time of Cancellation
    1752 - Base Support Structure Procurements Dahlgren Cancelled when Project Cancelled
WBS 18 - Field Period Assembly    
  1801 - FPA (ORNL) Cole Closed (Sept 2006)
  1802/1810/1815 - FP Assembly Oversight & Support/FPA Operations - Stations 1, 2, 3/FPA Operations - Station 5 Viola In Process at Time of Cancellation
  1803 - FP Assembly Tooling/Constructability - See Jobs 8203/1803 below Brown In Process at Time of Cancellation
  1804 - Metrology Hardware Raftopoulos Closed (Sept 2007)
  1805 - FP Assembly Hardware & Fixture Procurements Dudek In Process at Time of Cancellation
  1806 - FP Assembly Specs & Drawings Cole In Process at Time of Cancellation
WBS 19 - Stellartor Core Management & Integration    
 

1901 - Stellarator Core Management/Integration & Risk Mitigation Activities

Cole In Process at Time of Cancellation
WBS 2 - Auxiliary/Anciliary Systems    
  2101 - Fueling Systems Blanchard In Process at Time of Cancellation
  2201 - Torus Vacuum pumping Systems Blanchard In Process at Time of Cancellation
WBS 3 - Diagnostic Systems    
 

3101 - Magnetic Diagnostic Systems

Stratton

In Process at Time of Cancellation

  3601 - Edge & Divertor Diagnostics Systems Stratton In Process at Time of Cancellation
  3801 - Electron Beam Mapping Systems Stratton/Harris In Process at Time of Cancellation
  3901 - Diagnostic Systems Integration Stratton In Process at Time of Cancellation
WBS 4 - Electrical Power Systems    
  WBS 4 Jobs
  • Job 4101 - AC Power Systems
  • Job 4301 - DC Power Systems
  • Job 4401 - Control & Protection Systems
  • Job 4501 - Power Systems Design & Integration
Ramakrishnan In Process at Time of Cancellation
WBS 5 - Central Controls & Computing    
  5101 - Network & Fiber Optic Infrastructure Systems Sichta In Process at Time of Cancellation
  5201 - Central Instrumentation & Control Sichta In Process at Time of Cancellation
  5301 - Data Acquisition & Facility Computing Systems Sichta In Process at Time of Cancellation
  5401 - Facility Timing & Synchronization Systems Sichta In Process at Time of Cancellation
  5501 - Real Time Plasma Control Systems Sichta In Process at Time of Cancellation
  5601 - Central Safety Interlock Systems Sichta In Process at Time of Cancellation
  5801 - Central I&C Management & Integration Sichta In Process at Time of Cancellation
WBS 6 - Facility Systems    
  6101/6301 - Cooling Water/Utility Systems Dudek In Process at Time of Cancellation
  6201 - Cryogenic Systems Raftopoulos In Process at Time of Cancellation
  6401 - Bakeout Systems Kalish/Goranson In Process at Time of Cancellation
WBS 7 - Test Cell Prep & Machine Assembly    
  7101 - Shield Wall Modifications Perry Cancelled - Done as GPP Project
  7301 - Platform Design & Fabrication Perry In Process at Time of Cancellation
  7401/7451 - Machine Assembly  Planning & Oversight Perry In Process at Time of Cancellation
  7501/7503 - Construction Support/Machine Assy Ops Perry In Process at Time of Cancellation
  7601 - Machine Assembly Tooling Design/Fab Perry In Process at Time of Cancellation
WBS 81 - Project Management & Integration    
  8101 - Project Management @ PPPL Rej/Strkowsky In Process at Time of Cancellation
  8102 - Project Management @ ORNL Harris In Process at Time of Cancellation
  8998 - PPPL Direct Allocations Strykowsky In Process at Time of Cancellation
  DCMA Styksowsky Closed (Sept 2004)
WBS 82 - Project Engineering    
  8202 - Engineering Mgmt & Systems Engineering Heitzenroeder In Process at Time of Cancellation
  8203/1303 - Design Integration/Assembly Tooling Brown In Process at Time of Cancellation
  8204 - Systems Analysis & Technical Assurance Brooks In Process at Time of Cancellation
  8205 - Dimensional Control Coordination

 

Ellis In Process at Time of Cancellation
  8210 - Rebaselining Exercise Strykowsky In Process at Time of Cancellation
  8215 - Plant Design Perry In Process at Time of Cancellation
  8220 - Equipment Disposition/Facility Restorations Perry/Viola Will Complete as Part of Closeout
  8221 - Documentation for Closeout Heitzenroeder Will Complete as Part of Closeout
  8222 (CC1806) - Prepare Manuscripts for Peer Reviewed Papers Neilson Will Complete as Part of Closeout
WBS 84 - Project Physics    
  8401 - Project Physics @ PPPL Zarnstorf Closed (Sept 2006)
  8402 - Project Physics @ ORNL Lyon/Harris Closed (Sept 2006)
WBS 85 - Integrated System Testing    
  8501 - Integrated Systems Testing Gentile In Process at Time of Cancellation

               